TMI Update: Jan 14, 2024


Did you catch "The Meltdown: Three Mile Island" on Netflix?
TMI remains a danger and TMIA is working hard to ensure the safety of our communities and the surrounding areas.
Learn more on this site and support our efforts. Join TMIA. To contact the TMIA office, call 717-233-7897.

    

Act 129 Stakeholders,

At its Public Meeting this morning, the Commission approved a Tentative Order soliciting comments regarding potential models for a possible future demand response program.  With the Tentative Order, the Commission also released an amended version of the Statewide Evaluator’s Demand Response Study Final Report (originally released in May 2013).  I have included links to both documents below.  Comments will be due 30 days following the publishing of these documents in the Pennsylvania Bulletin, with reply comments due 45 days after the publishing date.

Peak Demand Cost Effectiveness Determination Tentative Order

Act 129 SWE Demand Response Study Final Report - Amended November 1, 2013

Questions regarding the technical aspects of these documents should be directed to me via email or by phone at 717-425-7583.  Questions regarding the legal aspects or regarding process issues should be directed to Kriss Brown at kribrown@pa.gov or 717-787-4518.

Thanks!
Megan
 
Megan G. Good
PA Public Utility Commission
Bureau of Technical Utility Services
Policy & Planning

Type: 

Act 129 Stakeholders,

At its Public Meeting this morning, the Commission approved a Tentative Order soliciting comments regarding potential models for a possible future demand response program.  With the Tentative Order, the Commission also released an amended version of the Statewide Evaluator’s Demand Response Study Final Report (originally released in May 2013).  I have included links to both documents below.  Comments will be due 30 days following the publishing of these documents in the Pennsylvania Bulletin, with reply comments due 45 days after the publishing date.

Peak Demand Cost Effectiveness Determination Tentative Order

Act 129 SWE Demand Response Study Final Report - Amended November 1, 2013

Questions regarding the technical aspects of these documents should be directed to me via email or by phone at 717-425-7583.  Questions regarding the legal aspects or regarding process issues should be directed to Kriss Brown at kribrown@pa.gov or 717-787-4518.

Thanks!
Megan
 
Megan G. Good
PA Public Utility Commission
Bureau of Technical Utility Services
Policy & Planning

Type: 

Act 129 Stakeholders,

At its Public Meeting this morning, the Commission approved a Tentative Order soliciting comments regarding potential models for a possible future demand response program.  With the Tentative Order, the Commission also released an amended version of the Statewide Evaluator’s Demand Response Study Final Report (originally released in May 2013).  I have included links to both documents below.  Comments will be due 30 days following the publishing of these documents in the Pennsylvania Bulletin, with reply comments due 45 days after the publishing date.

Peak Demand Cost Effectiveness Determination Tentative Order

Act 129 SWE Demand Response Study Final Report - Amended November 1, 2013

Questions regarding the technical aspects of these documents should be directed to me via email or by phone at 717-425-7583.  Questions regarding the legal aspects or regarding process issues should be directed to Kriss Brown at kribrown@pa.gov or 717-787-4518.

Thanks!
Megan
 
Megan G. Good
PA Public Utility Commission
Bureau of Technical Utility Services
Policy & Planning

Type: 

SUSQUEHANNA STEAM ELECTRIC STATION, UNITS 1 AND 2 - INTERIM STAFF EVALUATION AND REQUEST FOR ADDITIONAL INFORMATION REGARDING THE OVERALL INTEGRATED PLAN FOR IMPLEMENTATION OF ORDER EA-12-051, RELIABLE SPENT FUEL POOL INSTRUMENTATION {TAC NOS. MF0890 AND MF0891)

Download ML13295A606

Type: 

SUSQUEHANNA STEAM ELECTRIC STATION, UNITS 1 AND 2 - INTERIM STAFF EVALUATION AND REQUEST FOR ADDITIONAL INFORMATION REGARDING THE OVERALL INTEGRATED PLAN FOR IMPLEMENTATION OF ORDER EA-12-051, RELIABLE SPENT FUEL POOL INSTRUMENTATION {TAC NOS. MF0890 AND MF0891)

Download ML13295A606

Request for Withholding Information From Public Disclosure for Peach Bottom Atomic Power Station, Unit Nos. 2 and 3 (TAC Nos. ME9631 and ME9632)

Download ML13291A122

Type: 

NRC Meeting in Rockville Nov. 19 to Discuss Possible Changes to Emergency Response Requirements

Download PDF

Type: 

REQUEST FOR ADDITIONAL INFORMATION ASSOCIATED WITH NEAR-TERM TASK FORCE RECOMMENDATION 2.3, SEISMIC WALKDOWNS

Download ML13304B418

Type: 

Three Mile Island Station, Unit 1 - NRC Integrated Inspection Report 05000289/2013004

Download ML13301A503

Type: 

Response Regarding Licensee Phase 1 Staffing Submittals Associated with Near-Term Task Force Recommendation 9.3 Related to the Fukushima Dai-Ichi Nuclear Power Plant Accident

Download ML13233A183