Peach Bottom Station, Units 2 and 3 – NRC Security Baseline Inspection Report 05000277/2013403 and 05000278/2013403 (woOUO-SRI)

December 2, 2013

Mr. Michael J. Pacilio
Senior Vice President, Exelon Generation Company, LLC President and Chief Nuclear Officer, Exelon Nuclear 4300 Winfield Rd.
Warrenville, IL 60555

SUBJECT: PEACH BOTTOM ATOMIC POWER STATION, UNITS 2 AND 3 – NRC SECURITY BASELINE INSPECTION REPORT 05000277/2013403 AND 05000278/2013403

Dear Mr. Pacilio:

On October 25, 2013, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at your Peach Bottom Atomic Power Station. The inspection covered one or more of the key attributes of the security cornerstone of the NRC’s Reactor Oversight Process. The enclosed inspection report documents the inspection results which were discussed on October 25, 2013, with Mr. Patrick Navin, Plant Manager, and other members of your staff.

The inspection examined activities conducted under your licenses as they relate to security and compliance with the Commission’s rules and regulations and with the conditions of your licenses. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel.

No findings were identified during this inspection.

Download ML13340A810