NRC Extends Construction Deadline for MOX Fuel Fabrication Plant
NRC Extends Construction Deadline for MOX Fuel Fabrication Plant
The Nuclear Regulatory Commission signed an order Nov. 13 extending the completion deadline for a mixed-oxide fuel fabrication facility in South Carolina. Shaw AREVA MOX Services will have an additional 10 years, or until March 30, 2025, to finish building the facility at the Department of Energy’s Savannah River Site in Aiken.
MOX Services asked for the extension in May after a number of factors delayed construction, including lower than requested annual funding from Congress and delays in the delivery of components and key construction activities. The NRC issued the original 10-year construction authorization March 30, 2005. The extension does not expand the scope of work.
Type:
- Log in to post comments