Exelon, NRC to discuss Peach Bottom's Boraflex degradation management
JUNE 16, 2009 MEETING WITH EXELON NUCLEAR TO DISCUSS
MANAGEMENT OF BORAFLEX DEGRADATION AT PEACH BOTTOM
ATOMIC POWER STATION, UNITS 2 AND 3, AND THE ASSOCIATED
LICENSE AMENDMENT REQUEST UNDER REVIEW TO REVISE THE
TECHNICAL SPECIFICATIONS FOR THE SPENT FUEL POOL K
INFINITY VALUE.
FOR DETAILS ABOUT THE MEETING AND HOW TO ATTEND, READ MORE.
UNITED STATES
NUCLEAR REGULATORY COMMISSION
WASHINGTON, D.C. 20555-0001
May 28, 2009
MEMORANDUM TO: Harold K. Chernoff, Chief
Plant Licensing Branch 1-2
Division of Operating Reactor Licensing
Office of Nuclear Reactor Regulation
John D. Hughey, Project Manager
Plant Licensing Branch 1-2
Division of Operating Reactor Licensing I
Office of Nuclear Reactor Regulation
Tuesday, June 16, 2009
1:30 p.m. -5:00 p.m.
U.S. Nuclear Regulatory Commission
One White Flint North, Room 03-B4
11555 Rockville Pike
Rockville, MD 20852
Exelon Nuclear requested this meeting to discuss the License
Amendment Request currently under review to revise the Technical
Specifications related to the Spent Fuel Pool K-infinity value for the Spent
Fuel Pool at Peach Bottom Atomic Power Station (Agencywide
Documents Access and Management System Accession No.
ML081820302). Exelon will also provide an overview to the U.S. Nuclear
Regulatory Commission staff of the plans for managing borafJex
degradation in the Peach Bottom Atomic Power Station spent fuel pools.
This is a Category 1 public meeting. As such, the public is invited to
observe this meeting, and will have the opportunity to communicate with
the NRC staff after the business portion, but before the meeting is
adjourned.
Proprietary information will be discussed at certain times during this
meeting. These portions of the meeting will be closed to members of the
public who have not been granted access to the information by the owner
of the information, Northeast Technology Corporation (NETCo).
Interested members of the public can participate in this meeting via a
toll-free teleconference. For details, please call the NRC meeting contact.
John D. Hughey, NRR
301-415-3204
• Commission's Policy Statement on "Enhancing Public Participation in NRC Meetings" (67 FR 36920), May 28,2002.
H. Chernoff -2
PARTICIPANTS: Participants from the NRC include members of the Office of Nuclear
Reactor Regulation (NRR).
NRC Industry
H. Chernoff, NRR K. Lindquist, NETCo
J. Hughey, NRR M. Harris, NETCo
K. Wood, NRR P. Cowan, Exelon
G. Cranston, NRR et al. D. Helker, Exelon
T. Loomis, Exelon
A. Levin, Exelon
S. Hesse, Exelon et al.
The NRC provides reasonable accommodation to individuals with disabilities where appropriate.
If you need a reasonable accommodation to participate in a meeting, or need a meeting notice
or a transcript or other information from a meeting in another format (e.g., Braille, large print),
please notify the NRC's meeting contact. Determinations on requests for reasonable
accommodation will be made on a case-by-case basis.
To receive a summary of this meeting and begin receiving other plant-specific e-mail
distributions, you must subscribe to the Operating Reactor Correspondence electronic
distribution for this plant via http://www.nrc.gov/public-involve/listserver/plants-by-region.html.
Once subscribed, if you wish to discontinue receiving electronic distribution, you may
unsubscribe at any time by visiting the same web address above.
Docket Nos. 50-277,50-278
Enclosure:
Agenda
cc w/encl: Distribution via Listserv
AGENDA
FORTHCOMING PUBLIC MEETING WITH EXELON NUCLEAR
1:30 p.m. - 1:35 p.m.
1:35 p.m. - 2:05 p.m.
2:05 p.m. - 2:45 p.m.
2:45 p.m. - 3:00 p.m.
3:00 p.m. - 3:15 p.m.
3:15 p.m. - 4:00 p.m.
4:00 p.m. - 5:00 p.m.
Tuesday, June 16, 2009
1:30 p.m. -5:00 p.m.
Introductions
Boraflex degradation management at Peach Bottom Atomic Power
Station (Exelon)
Boraflex degradation management discussion (I\IRC/Exelon)
Summary of issues related to spent fuel pool criticality analyses
(NRC)
Public Comment
Break
Closed portion - discussion involving proprietary information
(NRC/Exelon)
The NRC provides reasonable accommodation to individuals with disabilities where appropriate.
If you need a reasonable accommodation to participate in a meeting, or need a meeting notice
or a transcript or other information from a meeting in another format (e.g., Braille, large print),
please notify the NRC's meeting contact. Determinations on requests for reasonable
accommodation will be made on a case-by-case basis.
To receive a summary of this meeting and begin receiving other plant-specific e-mail
distributions, you must subscribe to the Operating Reactor Correspondence electronic
distribution for this plant via http://www.nrc.gov/public-involve/listserver/plants-by-region.html.
Once subscribed, if you wish to discontinue receiving electronic distribution, you may
unsubscribe at any time by visiting the same web address above.
Docket Nos. 50-277 and 50-278
Enclosure:
Agenda
cc w/encl: Distribution via Listserv
DISTRIBUTION:
pUBLIc
RidsAcrsAcnw MailCTR Resource LPL1-2 RtF
RidsNrrAdro Resource PKrohn, RI
KWood, NRR
RidsNrrDorl Resource
RidsNrrPMJHughe~Resource RidsNrrDorlLpl1-2 Resource
RidsNrrPMPBamford Resource GCranston, NRR
C. Tucci, NRR
RidsNrrLAABaxter Resource
RidsOpaMail Resource
PMNS Resource
D. Screnci, OPA R-I
TWFN Receptionist
RidsOgcMailCenter Resource
RidsRgn1 MailCenter Resource
S. Campbell, EDO R-I
OWFN Receptionist
ADAMS Accession Number' ML091480028
OFFICE LPLI-2/PM LPLI-2/LA LPLI-2/BC
NAME JHuQhev ABaxter HChernoff
DATE 5/28/2009 5/28/2009 5/28/2009
OFFICIAL RECORD COPY
- Log in to post comments