Power plant brings reactor back online

From the Citizen's Voice:

PPL brought Unit 1 of the Susquehanna Nuclear Power Plant back on line Wednesday after flooding forced the utility to shut it down for roughly 20 days.

An estimated 950,000 gallons of Susquehanna River water flooded the basement of the plant's turbine building on July 16. The water flowed from hatches that allow access to the unit's condenser - where the river water cools steam leaving the turbine.

During the shutdown, PPL repaired the circulating water system and assessed equipment in the turbine building, plant manager Jeff Helsel said in a news release. The damage forced PPL to bring in extra help to dry and repair equipment shortly after the flood.

In addition, all the flood water was stored in tanks and tested several times for radiological and industrial contaminants.

Read more

Type: