NRC stalls key repairs for 32 years
From the Toledo Blade:
The NRC has reaffirmed several times since then that sumps at certain plants have been at risk of becoming overwhelmed by paint chips, insulation, and other free-floating debris that would form if an accident occurred. If those sumps fail, there wouldn’t be anything recirculating water to cool the reactors.
NRC Chairman Gregory B. Jaczko acknowledged Wednesday the agency “has been grappling with this issue for quite some time now.”
That’s an understatement. More than 18 years elapsed before regulators finally showed signs of getting serious about it in September of 1996. Then, they began drawing up plans for what’s known as Generic Safety Issue 191, an industrywide requirement to make the long-overdue sump fixes.
Type:
- Log in to post comments