News

 

By ANDREW MIGA (AP) 

 

BETHESDA, Md. — Federal regulators said Thursday they hope to resolve funding shortfalls with the owners of 26 nuclear plants, who aren't saving enough money to dismantle them when they've run their course.

Nuclear Regulatory Commission officials are reviewing action plans owners were asked to submit, explaining how they'd address funding shortfalls for shutting down reactors. NRC officials in June notified owners of the shortfalls, caused in part by the nation's financial meltdown.

 

 

Articles: 
Type: 

Aug. 12, 2009

Kalamazoo Gazette

BY ROD SMITH Special to Hometown Gazette

 

COVERT TOWNSHIP -- A second radioactive leak at the Palisades nuclear plant has been fixed.

``I'm happy to say we have found the source of the leak, and have repaired that.'' said Mark Savage, the public-affairs and communications director for Palisades.

The new leak was at a turn in a pipe and happened because of the failure of a weld, Savage said. The pipes and welds are stainless steel.

``We think it was during original construction,`` Savage said.

Type: 

 Notice of Availability of the Draft Revision to Generic 

Environmental Impact Statement for License Renewal of Nuclear Plants, 

Revision 1, NUREG-1437 and Public Meetings (see complete info from the Federal Register at bottom.) 

 

The Nuclear Regulatory Commission (NRC) is proposing to amend 

·        its environmental protection regulations by updating the Commission's 

·        1996 findings on the environmental impacts related to the renewal of a 

·        nuclear power plant's operating license. The Commission stated that it 

·        intends to review the assessment of impacts and update it on a 10-year 

·        cycle, if necessary. The proposed rule redefines the number and scope 

·        of the environmental impact issues which must be addressed by the 

·        Commission in conjunction with the review of applications for license 

·        renewal.

 

Type: 

 July 24, 2009

Decision will influence future of industry

By PETER BEHR of ClimateWire

The Obama administration is close to a decision on filling two vacancies on the Nuclear Regulatory Commission, according to industry and congressional sources. The appointments would come at a pivotal time for the industry's hopes of a revival, as NRC weighs operating license applications for a handful of new reactors and a review of its waste fuel policy.

The administration is believed to have settled on former Energy Department official William Magwood and Massachusetts Institute of Technology professor George Apostolakis as the nominees. Both would be welcomed by the industry, officials said.

Type: 

 Eric Epstein has submitted a memo challenging sections of the petition of PPL Electric Utilities Corporation for Approval of an Energy Efficiency and Conservation Plan.

As a PPL customer, Epstein questions "the legality and appropriateness of PPL’s Time of Use programming," among other issues. 

Type: 

July 23, 2009

HARRISBURG – According to an audit report released today by the Pennsylvania Public Utility Commission (PUC), PPL Electric Utilities Corp. (PPL) may realize yearly savings up to $1.9 million and one-time savings of $9.8 million by implementing recommendations contained in the audit.

The Commission voted 5-0 to make the audit report and the company’s implementation plan public.  The Focused Management and Operations Audit analyzed and evaluated management performance in 12 areas.  The audit was conducted by the PUC’s Bureau of Audits Staff.

The audit makes 23 recommendations to the company for improvement.  The company’s implementation plan accepted all 23 of the recommendations.

Type: 

The Pennsylvania Public Utility Commission will have a hearing for public input concerning approval of and Energy Efficiency and Conservation Plan for PPL Electric Utilities, on July 30 at 6 p.m. in Bethlehem, Pa. at City Council Chambers. 

Articles: 
Type: 

 

WAYNE PARRY

The Associated Press

ATLANTIC CITY, N.J. - The U.S. Nuclear Regulatory Commission started a special investigation Thursday into an emergency shutdown of the nation's oldest nuclear power plant.

Over the weekend, the Oyster Creek Nuclear Generating Station had to shut down when severe thunderstorms knocked out power to the area.

Type: 

 July 17, 2009 

Type: 

By Ad Crable 

Lancaster New Era Staff

 

A control-room operator at the Peach Bottom nuclear plant spent 10 minutes reading a novel, the U.S. Nuclear Regulatory Commission alleges.

The violation of federal regulations came to light while the NRC was at the plant for an inspection prompted by a 2007 incident in which security guards at the plant were filmed sleeping in an off-duty room where they were allowed to rest but not sleep.

The latest incident occurred in July 2007, according to a notice of violation sent to Peach Bottom owner Exelon Generation on Thursday.

Type: 